Test- und Abnahmeleitfaden für Richtproben

A successful straightening sample is not simply a part that looks straight after one press. The test must prove that an agreed workpiece family can be measured, corrected and accepted without unacceptable damage, under conditions that can be reproduced in production.

This guide separates early feasibility trials, engineering sample validation, factory acceptance testing (FAT) and site acceptance testing (SAT). It also explains what data is needed before a supplier can convert a promising sample into a defendable machine guarantee.

Contact measurement and rotation station used for shaft straightening validation

Four Different Validation Stages

BühneMain QuestionTypical OutputWhat It Does Not Prove Alone
Feasibility trialCan this workpiece be measured and corrected without obvious damage?Initial method, Datum, tooling and risk assessmentProduction capability or final cycle time
Engineering sample testWhat process window works across representative parts?Sample matrix, recipes, before/after data and limitsComplete production machine readiness
Factory Acceptance Test (FAT)Does the built machine meet the agreed factory test specification?Witnessed FAT protocol, Ergebnisse, open-item list and release decisionPerformance after transport and site installation
Site Acceptance Test (SAT)Does the installed machine perform in the customer’s real environment?Site results, gauge correlation, training and final acceptanceConditions outside the agreed site and product scope

Do not use one successful feasibility sample as evidence that every model, batch, incoming bend and production condition is guaranteed.

Freeze the Measurement Definition First

The test cannot be valid until both parties agree what “straight” means. Geradlinigkeit, Rundlauf, total runout and shop-floor TIR are different characteristics and may produce different values.

Before testing, define:

  • controlled characteristic and drawing tolerance;
  • applicable drawing standard and edition;
  • datum features or support reference;
  • probe surface, axial stations and probe path;
  • free-state or clamped-state condition;
  • Rotationsgeschwindigkeit, filtering and reading rule where relevant;
  • excluded features such as keyways, Rillen, teeth or holes;
  • customer reference gauge and machine gauge;
  • acceptance decision near the tolerance limit.

See Wellengeradheit vs. Rundlauf vs. TIR for the measurement distinctions that must be resolved before the test protocol is signed.

Build a Representative Sample Matrix

Randomly sending a few convenient parts creates weak evidence. The sample set should cover the real product envelope and the conditions most likely to fail.

Sample DimensionMinimum Coverage Question
GeometrieShortest/longest, smallest/largest diameter, thinnest wall, most complex feature set
MaterialLowest/highest strength or hardness, relevant alloy and heat-treatment batches
Eingehende VerformungNormal distribution, worst expected bend, multiple-bend and torsion cases
Surface conditionRaw, turned, hardened, ground, coated or otherwise finished states
Functional featuresGear, Spline, Faden, Keilnut, flange, radial hole, weld or thin-wall section
ToleranceNormal parts plus samples near the final acceptance boundary
Production modelEvery recipe/tooling family or justified worst-case representatives
HandhabungLoading orientation, mixed models and parts most difficult to separate or locate

The matrix should record how each sample was selected. A “worst case” without a drawing, material record or measured incoming value is not traceable evidence.

Pre-Test Readiness Checklist

Workpiece Information

  • Approved drawing and revision are available.
  • Material, Härte, heat-treatment state and process stage are recorded.
  • Incoming bend or runout is measured before correction.
  • Protected support, measuring and pressing/rolling zones are marked.
  • Samples are identified individually and cannot be mixed after testing.

Measurement Readiness

  • Customer and supplier agree the datum and characteristic.
  • Gauges have valid calibration status appropriate to the test plan.
  • Fixtures, centers, contacts and probe surfaces are clean and repeatable.
  • Repeat readings have been taken to expose unstable setup or operator influence.
  • A correlation method is defined before comparing machine and customer results.

Process Readiness

  • The selected press or roller concept matches the workpiece geometry.
  • Initial stroke, Gewalt, roll gap, angle or other limits are conservative.
  • Sicherheit, guarding and abnormal-part reaction are ready for the test.
  • The data sheet and pass/fail rule are agreed before the first result is seen.

For method selection, review Press Straightening vs Roller Straightening.

Recommended Sample-Test Sequence

1. Identify and Inspect the Sample

Record sample ID, drawing revision, material/batch, Prozessstufe, Abmessungen, hardness where relevant and visible surface condition. Photograph or document pre-existing damage so it is not confused with straightening marks.

2. Measure the Incoming Condition

Use the agreed fixture, datum and stations. Repeat at least enough measurements to identify unstable seating or obvious gauge variation. Record the full result, not only the single worst point.

3. Apply a Controlled Initial Correction

Begin inside a conservative process window. For point press straightening, record support positions, press location, angular position, stroke and force where available. For roller straightening, record roll set, gap, angle, speed, guide and pass information.

Controlled press correction applied to a slender motor shaft

4. Remeasure with the Same Method

Use the same datum, fixture and measuring stations. If a second correction is allowed, the acceptance plan should define maximum iterations, stroke/force or pass limits instead of letting the operator continue until a favorable number appears.

5. Inspect Part Integrity

Check contact marks, cracks, dents, ovality, thread/tooth damage, coating condition and other functional risks. A part that meets runout but has a damaged bearing journal or thin wall is not acceptable.

6. Record Cycle and Handling Evidence

Separate automatic machine time, loading/unloading, Messung, correction iterations, model change and manual inspection. A short edited video is useful visual evidence but is not a statistically valid cycle-time study.

The video shows one automatic small-shaft loading and press-straightening sequence. It demonstrates equipment flow only; a final cycle guarantee requires a defined start/end point, representative parts and repeated timed observations.

7. Classify the Result

Use one of the pre-agreed outcomes: passieren, fail, engineering review or retest after a documented correction to the setup. Do not silently remove failed samples from the report.

Straightened worm shafts moving through the output and result-sorting area

Minimum Per-Part Data Record

Record FieldWarum es wichtig ist
Sample ID and drawing revisionPreserves traceability
Material, batch and hardness/process stateExplains springback and crack-risk variation
Incoming values at all stationsDefines the actual challenge
Datum, fixture and gaugeMakes the result reproducible
Recipe/tooling versionConnects the result to machine settings
Correction count, positions and limitsShows how the result was achieved
Final values at all stationsPrevents selective reporting
Surface/integrity inspectionConfirms the part remains usable
Automatic and total cycle observationsSeparates machine speed from complete handling time
Final dispositionPass, fail, review or retest with reason

Gauge Correlation and Decision Rules

Two gauges can be individually repeatable and still disagree because they realize the datum differently or evaluate different surfaces. Correlation should include good, borderline and bad samples across the model range.

Correlation ItemAgreement Needed
Datum realizationCenters, journals, V-blocks, functional gauge or CMM construction
Measuring pointsSame axial stations, surfaces and excluded zones
Part conditionTemperature, cleanliness, free/clamped state and elapsed time
Reading methodPeak-to-peak, fitted axis, filtering and rounding
RepeatabilityRepeated readings on both systems
Borderline resultGuard band, recheck or engineering disposition rule
Reference methodWhich gauge controls FAT, SAT and final contractual acceptance

When a measured value is close to the tolerance limit, measurement uncertainty and the agreed conformity decision rule matter. The quotation and protocol should state the rule instead of assuming every displayed value can be treated as exact.

From Sample Test to Machine Specification

A validated sample test should change the proposal from generic marketing language into an engineering specification.

Sample EvidenceSpecification Output
Proven workpiece envelopeCovered model/size/material family
Agreed datum and gauge correlationMachine measurement and reference acceptance method
Correction responsePress/roll capacity, resolution and process limits
Protected feature studyUnterstützung, measuring and correction tooling design
Cycle observationsDefined takt basis and excluded manual activities
Failure behaviorNOK route, stop limits and operator/engineering review
Data needsTraceability fields, storage and interface scope
Changeover testWerkzeuge, recipe and setup-time requirements

Anything not tested should remain an assumption, option or open engineering item—not a guaranteed performance statement.

Factory Acceptance Test (FAT)

FAT is performed at the supplier’s factory against an agreed protocol before shipment. The exact scope must be adapted to the machine and contract.

FAT Scope

  • machine configuration matches approved drawings and purchase specification;
  • guards, Verriegelungen, emergency stops and defined safety functions are tested;
  • utilities, axes, Sensoren, press/roll functions and abnormal alarms operate;
  • agreed workpiece models and changeovers are demonstrated;
  • measurement correlation and acceptance logic are checked;
  • representative production run and cycle measurement follow the protocol;
  • NOK handling, data recording and interfaces are exercised;
  • manuals, drawings, backups, spare parts and training records are reviewed;
  • deviations are listed with owner, action and closure evidence.

A FAT should not be reduced to “the machine ran successfully.” Each acceptance point needs an observable test, measurable criterion, recorded result and disposition.

Site Acceptance Test (SAT)

SAT verifies the installed system after transport, installation and connection to the customer’s real utilities, material flow and quality process.

SAT Adds Site-Specific Evidence

  • foundation, level, utilities and environmental conditions;
  • upstream/downstream equipment and real loading logistics;
  • customer production material and approved recipes;
  • customer reference gauge and local quality workflow;
  • network, MES or traceability interfaces where included;
  • Operator, maintenance and quality training;
  • production-like run under the agreed site conditions;
  • closure of FAT open items affected by installation.

SAT is not a second opportunity to introduce new requirements that were absent from the contract. Changes should follow a documented variation process.

FAT/SAT Acceptance Table Template

Test ItemVerfahrenAcceptance CriterionEvidenceErgebnis / Disposition
Workpiece measurementAgreed gauge and stationsDefined tolerance and decision ruleBefore/after data sheetPass/fail/open
Surface integrityVisual or specified inspectionNo prohibited damagePhotos/inspection recordPass/fail/open
ZykluszeitDefined start/end and repeated runsContract value under stated conditionsTimestamped run logPass/fail/open
Model changeApproved sequence and toolingRequired setup and correct recipeWitness recordPass/fail/open
NOK handlingChallenge part or simulated faultCorrect stop/sort/alarm responseEvent log/videoPass/fail/open
Safety functionApproved safety test procedureRequired response achievedSigned checklistPass/fail/open
TraceabilityTest part and data exportRequired fields stored/transferredFile/interface recordPass/fail/open

Managing Deviations and Open Items

Every deviation should have:

  • unique ID and requirement reference;
  • observed condition and objective evidence;
  • impact on safety, quality, delivery and production;
  • temporary disposition if operation continues;
  • responsible owner and target date;
  • corrective action and retest method;
  • closure approval by the authorized parties.

Do not convert an unresolved performance failure into a vague “optimization after shipment” note. Shipment and final acceptance gates should state which open items are allowed and which are blocking.

Common Testing Mistakes

  • Testing only nominal parts and excluding worst-case samples.
  • Changing the datum or gauge after seeing an unfavorable result.
  • Reporting only successful parts or the best final value.
  • Mixing machine cycle time with complete operator handling time.
  • Using customer tolerance as if it were already demonstrated capability.
  • Ignoring contact marks, cracks, ovality or feature damage.
  • Treating one video or one sample as production validation.
  • Leaving FAT/SAT criteria until the machine is already built.
  • Accepting displayed values near the limit without an agreed decision rule.

Information to Send for a Sample Study

Please provide:

  • drawings, revisions and model matrix;
  • Material, hardness and heat-treatment condition;
  • incoming bend/runout distribution and known worst cases;
  • final characteristic, Toleranz, datum and inspection work instruction;
  • protected surfaces and allowed support/correction zones;
  • production stage, volume, takt and loading requirements;
  • representative samples covering the full envelope;
  • required traceability and data interface;
  • target FAT/SAT location, witness needs and documentation language.

FAQ

How many samples are enough?

There is no universal number. The set must cover geometry, Material, incoming deformation, tolerance boundary and production variation. A small feasibility set can select a concept, but it cannot establish broad production capability.

Can the supplier use its own gauge?

Ja, if the method is agreed and correlated with the customer’s reference method. The protocol must state which result controls acceptance and how borderline disagreements are handled.

Does a passed FAT mean the machine is finally accepted?

Only according to the contract. FAT proves the agreed factory scope. SAT may still be required to verify installation, utilities, interfaces, customer material and site operation.

Should failed samples stay in the report?

Ja. They define the process boundary and help distinguish machine limits, sample defects, setup problems and measurement disagreement.

Can cycle time be guaranteed from one run?

NEIN. Define the cycle start/end, part condition, correction distribution, loading and inspection scope, then use repeated observations across representative samples.

What happens if the customer changes the drawing after testing?

The new revision requires an impact review. Changes to tolerance, Datum, Geometrie, material or protected zones may require new samples, Werkzeuge, software or commercial scope.

Turn Sample Evidence into an Acceptance Plan

The purpose of a sample test is not to create a favorable demonstration. It is to discover the reproducible process window, measurement agreement, risks and limits before they become contractual obligations.

Kontaktieren Sie StraighteningTech with your drawing, measurement method and representative sample matrix. Our solution team can prepare a feasibility study and project-specific sample, FAT and SAT plan.

Inhaltsverzeichnis
Nach oben scrollen